Wall and ceiling painting in a research building — Space Campus, Belval
Client
POECKES S.à r.l.
Package
Interior painting
Location
Belval, Esch-sur-Alzette
Year
2026
Status
Work in progress
At the Space Campus in Belval, the DTVC building is a research and analysis facility being built for the Fonds Belval, the public-sector client. The general contractor POECKES awarded QUASART the painting package: walls, ceilings and stair soffits, from the standard rooms to two technical halls with more than seven metres of clear height.
QUASART works as a subcontractor to the general contractor, with its own teams and partner companies under its coordination, on a site where the building services trades are working at the same time. The package’s resin floors are entrusted to a specialist partner company. The photos on this page show progress between May and October 2026.
What the bill of quantities specifies
The package follows the client’s bill of quantities and its finishes layout drawings. On plasterboard partitions and plastered walls, a renovation nonwoven is bonded as a surface reinforcement before two coats of wall paint. Smooth concrete walls and exposed masonry receive two coats of paint, as do the bare concrete ceilings and the stair soffits.
In the bill of quantities, the package covers almost 4,800 m² of walls and ceilings: around 1,980 m² of plasterboard and plastered walls, 1,376 m² of concrete and masonry walls, 1,410 m² of ceilings and 30 m² of stair soffits.
Our teams mainly used two PROFITEC paints: P107 Ratio DIN, a matt white interior paint, and P818, a white paint with built-in primer. More than a hundred 12.5-litre buckets were delivered between May and September 2026.
Painting above seven metres
Clear heights vary widely from room to room: 3.20 m on the upper floor, 3.60 m on the ground floor, and 7.18 m and 7.58 m in the two technical halls. The upper parts of the halls are painted from an aluminium mobile access tower compliant with EN 1004-1, with a working height of 7.50 m.
Before its first use, an acceptance and commissioning report was drawn up for the tower in line with the manufacturer’s instructions; it is kept on site.
Resin floors, entrusted to a specialist partner
The package also includes the floors of the plant rooms and of the areas sensitive to electrostatic discharge. For these, the bill of quantities specifies an epoxy resin over a primer, made conductive (ESD) by copper strips bonded to the dry primer, with coved skirtings. This item — almost 1,100 m² of floors and 285 m of skirting in the bill of quantities — is entrusted to a specialist partner company.
QUASART coordinates this item with the painting of the walls and ceilings.
Painting around building services
In the technical halls, much of the wall and ceiling surface is painted with the ventilation ducts, cable trays, pipework and equipment already installed. The equipment stays protected during painting — covers on the diffusers, sheeting over the machines, floor protection — and the paint is taken right up to the brackets and penetrations.
Work proceeds alongside the building services trades: the sequence of areas is agreed with the general contractor as the other trades progress.
The project in pictures











Questions about this project
Why bond a nonwoven lining before painting?
On plasterboard and plastered walls, the bill of quantities specifies a renovation nonwoven as a surface reinforcement. Bonded to the substrate, it evens out the surface appearance and provides a uniform base for the two coats of wall paint that go over it.
How do you paint walls more than seven metres high?
From an aluminium mobile access tower compliant with EN 1004-1, here with a working height of 7.50 m. Before its first use, an acceptance and commissioning report is drawn up for the tower, in line with the manufacturer’s instructions.
Can you paint once the building services are installed?
Yes, as in large parts of this building’s halls. The equipment is protected during the works — covers, sheeting, floor protection — and the paint is taken right up to the brackets and penetrations, in coordination with the general contractor and the building services trades.
Does QUASART carry out the package on its own?
QUASART is responsible for the painting package as a subcontractor to the general contractor POECKES. Its teams work alongside partner companies, under QUASART’s coordination; the resin floors are entrusted to a specialist partner company.
Which paints were used?
Mainly two PROFITEC paints: P107 Ratio DIN, a matt white interior paint, and P818, a white paint with built-in primer. On plasterboard and plastered walls, they go over a renovation nonwoven, as specified in the bill of quantities.