Metal cladding in ST 300 steel boards — Rout Lëns, Esch-sur-Alzette
Client
CLE S.A.
Architect
Fabeck Architectes
Package
Metal cladding
Location
Rout Lëns, Esch-sur-Alzette
Year
2026
Status
Work in progress
In Esch-sur-Alzette, the new Rout Lëns district is being built on the Terres Rouges site. For the general contractor CLE, QUASART is installing the metal cladding on building 29B in block 14, developed by IKO Real Estate: a ventilated facade in pre-painted steel boards, laid vertically from the first to the fourth floor.
The contract, signed in March 2026, covers around 1,200 m² of facade and 1,000 linear metres of finishing profiles. QUASART installs the substructure, boards and profiles, and supplies the screws and shims.
A ventilated facade in steel boards
The cladding is the ArcelorMittal ST 300 board: pre-painted sheet steel at least 1 mm thick, in matt RAL 9007, laid vertically. It was specified in the execution documents because it interlocks at window sills without having to be angled in.
Behind the boards, a ventilated air gap separates the cladding from the membrane and insulation. Made-to-measure pre-painted sheet-metal profiles finish every edge and opening: starter profile, drip edge, flashings, jamb linings and corner trims, with a rodent mesh at the foot of the cladding.
A levelled and shimmed substructure
The boards are fixed to a horizontal substructure of 1.5 mm galvanised steel omega rails (Z450), screwed to the timber backing of the facade. Each rail is levelled and shimmed to give a true fixing plane, a prerequisite for neatly aligned vertical joints.
The fixings are sized on the basis of a wind-load calculation: a building about 16.5 m high, wind zone 2, and a combined board-and-substructure weight of about 13.5 kg/m².
A housing project, facade by facade
Block 14 combines several facade types: render, timber and metal. The junctions between the metal cladding and the adjoining work — rendered facades, windows and doors, metalwork — follow the working and board-layout drawings approved for the package.
The work is progressing facade by facade: as of autumn 2026, several facades are fully clad and work on the others is under way.
The project in pictures









Questions about this project
What is an ST 300 cladding board?
A pre-painted sheet steel board from ArcelorMittal, at least 1 mm thick, designed for rainscreen cladding. It can be laid with vertical or horizontal joints; at Rout Lëns it is laid vertically, in RAL 9007.
Why an omega-rail substructure?
The galvanised steel omega rails provide the fixing plane for the boards and create the air gap of the ventilated facade. Levelled and shimmed, they take up irregularities in the backing so the boards line up evenly.
How are the fixings sized?
By a wind-load calculation carried out for the building: a height of about 16.5 m, wind zone 2, and a combined board-and-substructure weight of about 13.5 kg/m².
Is the project finished?
No, it is still in progress. Several facades are already clad; the photos show progress from April to September 2026.